This has been completed without incident.
On Mon, Nov 19, 2012 at 4:18 PM, Ray Soucy <[log in to unmask]> wrote:
> Where: Orono Datacenter
> When: Nov 21, 2012 0700
> Expected Duration: < 1 min.
> Scope: Networking, Rack 122
>
> Summary:
> Secondary power for the network switch will be relocated to a different circuit. Switch has redundant power and no disruption of service is expected.
>
> Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
--
Ray Patrick Soucy
Network Engineer
University of Maine System
T: 207-561-3526
F: 207-561-3531
MaineREN, Maine's Research and Education Network
www.maineren.net