This maintenance was completed successfully. Adam Paradis Virtualization Administrator | Data Center Operations University of Maine System 207-581-3529 On Mon, Jun 15, 2020, 8:18 AM DCO <[log in to unmask]> wrote: > *What is happening?* > > On Wednesday, June 17, 2020, from 6 a.m. - 8 a.m., Data Center Operations > will be performing physical cable relocations on a set of existing disk > shelves from old to new NetApp controllers. > > *Why is this work necessary?* > > A migration process is currently underway from old to new controllers and > evacuation of these disk shelves is required to move equipment and data. > > *What happens if this work is unsuccessful?* > > The relevant disk shelves will be evacuated; as such any issues will not > compromise production workloads on these units. Although if difficulties > are encountered then the connection to the new nodes will be removed. > > Please email [log in to unmask] or call 207-581-3550 if there are any > questions or concerns. > > Data Center Operations | US:IT > University of Maine System > 207-581-3550 >