NETANN-L Archives

- NETANN-L - Networkmaine Network Announcement List

NETANN-L@LISTS.MAINE.EDU

Options: Use Forum View

Use Monospaced Font
Show Text Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
Adam Paradis <[log in to unmask]>
Reply To:
- NETANN-L - Networkmaine Network Announcement List <[log in to unmask]>
Date:
Wed, 24 Jun 2020 20:59:33 -0400
Content-Type:
text/plain
Parts/Attachments:
text/plain (37 lines)
This maintenance was completed successfully.

*Adam Paradis*
Virtualization Administrator | Data Center Operations
University of Maine System
207-581-3529


On Wed, Jun 24, 2020 at 1:07 PM DCO <[log in to unmask]> wrote:

> *What is happening?*
>
> On Wednesday, June 24, 2020, from 8:00 PM to 9:00 PM, Data Center
> Operations will be initiating a temporary NetApp controller failover (also
> known as a takeover/giveback).
>
> *Why is this work necessary?*
>
> This failover is an attempt to clear failed replication jobs that are
> preventing volume migrations to new NetApp controllers.
>
> *What happens if this work is unsuccessful?*
>
> If the failover to the peer controller causes any issues then all services
> will immediately be reverted to the original node.
>
> No interruption is expected as all storage traffic will be served through
> the other controller until the process is complete, at which point the home
> node will become active again.
>
> Please email [log in to unmask] or call 207-581-3550 if there are any
> questions or concerns.
>
> Data Center Operations
> US:IT | University of Maine System
>