Subject:
From:
Reply To:
- NETANN-L - Networkmaine Network Announcement List <[log in to unmask]>
Date:
Mon, 13 Jun 2022 14:27:50 -0400
Content-Type:
text/plain
Parts/Attachments:
text/plain (23 lines)
*What is happening?*

On Wednesday, June 15th, 2022, at 7:00 AM, Data Center Operations will
upgrade the VMware EVC level for the primary Orono host cluster on UMSVC.
There will be no interruption to production workloads at the time of this
change, however VMs will eventually need to be restarted to take advantage
of the new EVC configuration.

*Why is this work necessary?*

This upgrade will allow newer VM CPU architecture requirements to be met.

*What happens if this work is unsuccessful?*

NA

Please email [log in to unmask] or call 207-581-3550 if there are any questions
or concerns.

Data Center Operations | US:IT
University of Maine System
207-581-3550