This maintenance is complete
On Wed, Nov 28, 2018 at 5:21 PM Ray Soucy <[log in to unmask]> wrote:
> Where: UM
> Start: 12/02/2018 05:00 am
> End: 12/02/2018 07:00 am
> Scope: Campus Core Switching
>
> Summary:
>
> A software update will be applied to address a compatibility issue
> affecting buildings which use older equipment which can sometimes disrupt
> communication.
>
> The following downstream buildings will be affected:
>
> Boardman
> Athletic Buildings (Filed House, Arena, Stadium)
> Stewart
> Bennett
> Stevens
> Cutler
> Crosby
> Machine Tool Lab
>
> Proving no problems are encountered an additional maintenance event will
> be planned to upgrade the rest of the UM campus.
>
> Networkmaine Contact Info:
> NOC 581-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
--
Ray Patrick Soucy
Senior Cyber Security Engineer
Networkmaine, University of Maine System US:IT
207-581-3526