This maintenance has been completed successfully.
Data Center Operations
University of Maine System
207-581-3550
On Fri, Feb 24, 2023 at 9:23 AM DCO <[log in to unmask]> wrote:
> *What is happening?*
>
> On Sunday, February 26th, 2023 from 6:00 AM to 9:00 AM Data Center
> Operations will be performing a firmware upgrade on the Orono data center
> UCS equipment (fabric interconnects, blade chassis, blade servers,
> management platform), all of which provides the backing for VMware hosts at
> that location. The upgrade process is not expected to cause any disruption
> in service due to the active/standby configuration of the equipment.
>
> *Why is this work necessary?*
>
> This firmware upgrade will address several security issues as well as
> provide feature updates for the UCS platform hardware.
>
> *What happens if this work is unsuccessful?*
>
> If the upgrade process is unsuccessful the UCS platform hardware will
> automatically revert to a backup version of firmware.
>
> Please email [log in to unmask] or call 207-581-3550 if there are any
> questions or concerns.
>
> Data Center Operations | US:IT
> University of Maine System