Maintenance is complete. We went 30 minutes over the expected time due to
some caveats we came across, however operations are now back to normal.
Thanks,
--Brandon
On Monday, October 17, 2016, Brandon Glenn <[log in to unmask]> wrote:
> Where: Portland Data Center
> When: Oct 23, 2016 5 AM
> Expected Duration: 1hr
> Scope: UMS-wide inbound-outbound calling
>
> Summary:
> We will be performing maintenance at our Portland data center that
> will impact telephone calls inbound and outbound across UMS. Please plan
> accordingly.
>
> Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
--
--
Brandon J. Glenn ([log in to unmask])
Network Engineer
Networkmaine
University Services
University of Maine System
235 Science Building
Portland, ME 04104
Phone: (207)-561-3577
Fax: (207)-561-3597