This maintenance is complete.
On Wed, Apr 17, 2019 at 3:46 PM Ray Soucy <[log in to unmask]> wrote:
> Where: Orono Campus
> Start: 04/21/2019 05:00 am
> End: 04/21/2019 07:00 am
> Scope: Campus-Wide - Core Switching Software Upgrade
>
> Summary:
>
> A software upgrade will be applied to campus core switches at the
> University of Maine.
>
> This will impact connectivity campus-wide during the window, but
> disruption of service is expected to be limited to 15 to 30 min per area.
>
> There will be no impact to data center connectivity.
>
>
>
> Networkmaine Contact Info:
> NOC 581-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
--
Ray Patrick Soucy
Senior Cyber Security Engineer
Networkmaine, University of Maine System US:IT