This work has been delayed due to an unexpected difficulty not
directly related to the target platform. It may be rolled into the
upcoming service-affecting maintenance.
On Fri, Oct 7, 2016 at 9:49 AM, Drew Northup <[log in to unmask]> wrote:
> Where: US:IT Orono Datacenter
> When: 5:30 AM - 7:00 AM
> Expected Duration: Less than 20 minutes, starting around 6:00. No
> interruption of service expected.
>
> Scope: Sysadmin and system utilities on Doodlebug and Carnelian, which
> primarily provide file shares and computer-lab LDAP for UMF.
>
> Summary: This is the first batch of patches that need to be applied to
> these systems to bring them up to date. Only patches expected NOT to
> interfere with service delivery will be applied this round (things
> such as command line utilities and package manager software).
> Known service affecting patches, such as those requiring a reboot,
> will be applied at a later date, currently targeting October 16th or
> 23rd. (Announcement for that work expected by the end of the work day
> on the 12th or 19th, respectively, if it is not delayed.)
>
> Note: UMF Campus Services was consulted and the UTSC is being notified.
>
> ITS/Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> UMF Campus Services
>
> --
> ---------------------------------+--------------------------------------
> Drew Northup | Technical Support Specialist
> University of Maine System | [log in to unmask]
> Computing Center | phone: (207) 561-3513
> Orono, ME 04469 | fax: (207) 561-3531
--
---------------------------------+--------------------------------------
Drew Northup | Technical Support Specialist
University of Maine System | [log in to unmask]
Computing Center | phone: (207) 561-3513
Orono, ME 04469 | fax: (207) 561-3531
|
|
|