NETANN-L Archives

- NETANN-L - Networkmaine Network Announcement List

NETANN-L@LISTS.MAINE.EDU

Options: Use Forum View

Use Monospaced Font
Show Text Part by Default
Condense Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Sender:
- NETANN-L - Networkmaine Network Announcement List <[log in to unmask]>
Subject:
From:
Chris Thibault <[log in to unmask]>
Date:
Tue, 22 Jan 2019 08:32:28 -0500
Message-ID:
Reply-To:
Parts/Attachments:
text/plain (17 lines)
Where: USM Portland
Start: 01/23/2019 05:00 am
End: 01/23/2019 07:00 am
Scope: Loss of power redundancy

Summary: 
	We will be installing some new power circuits in the Portland Data Center and power panel UP1 will need to be turned off for the electrician to perform the work.

There is no expected impact from the work as all essential hardware has redundant power.


Networkmaine Contact Info: 
	NOC 581-3587

Local/Campus Contact Info during this window of work: 
	[log in to unmask]