Although the switch upgrades were a success, a number of USM services were
affected. Cleanup is ongoing.
Thanks,
--Brandon
--
Brandon J. Glenn ([log in to unmask])
Network Engineer
Networkmaine
University Services
University of Maine System
235 Science Building
Portland, ME 04104
Phone: (207)-561-3577
Fax: (207)-561-3597
On Thu, Feb 5, 2015 at 11:22 AM, Brandon Glenn <[log in to unmask]> wrote:
> This maintenance may impact ALL USM services.
>
> Please plan accordingly.
>
> Thanks,
>
> --Brandon
>
> --
> Brandon J. Glenn ([log in to unmask])
> Network Engineer
> Networkmaine
> University Services
> University of Maine System
> 235 Science Building
> Portland, ME 04104
> Phone: (207)-561-3577
> Fax: (207)-561-3597
> On Feb 4, 2015 10:08 PM, "Brandon Glenn" <[log in to unmask]> wrote:
>
>> Where: Portland Data Center
>> When: Feb 08, 2015 7 AM
>> Expected Duration: 1hr
>> Scope: USM Data Center Operations
>>
>> Summary:
>> We will be performing network maintenance in the Portland data
>> center. Some USM web services may be impacted by the maintenance. Please
>> plan accordingly.
>>
>> Networkmaine Contact Info:
>> NOC 561-3587
>>
>> Local/Campus Contact Info during this window of work:
>> NONE / Unknown at this time
>>
>
|
|
|