Maintenance has been canceled due to the Board of Trustees meeting int
Augusta on March 17th. This maintenance was to replace a failing piece of
hardware, so the maintenance will be rescheduled at a later date.
Thank you,
Corey Lavoie
============================================
== Senior Communications Specialist
== Communications and Network Services
== Maine School and Library Network
== University of Maine System
============================================
On Fri, Mar 1, 2013 at 1:19 PM, Corey D Lavoie <[log in to unmask]> wrote:
> Where: Orono Campus / UMS-ITS Orono Data Center
> When: Mar 17, 2013 5:00 AM
> Expected Duration: 5hrs
> Scope: UMS Connections in/out of Orono
>
> Summary:
> This is an advanced notice. During the maintenance window we will
> be replacing the hardware for GW-O-Neville.
>
> This will create an outage for the Orono Campus (UM IP Phones as well) and
> access to the Orono Data Center from the rest of the University of Maine
> System. This will affect access to service such as MaineStreet,
> http://www.maine.edu, and all other services running out of the Orono
> Data Center.
>
> Total downtime should be around two hours, but remaining time in the
> maintenance window may be needed to resolve any issues that may be related
> to the maintenance.
>