Where: UMA - Bangor Campus
When: Jan 16, 2013 5:00 AM
Expected Duration: 2hrs
Scope: Network connectivity in all buildings

Summary: 
	During the maintenance window we will be system upgrades to the switches in all buildings.  

We will be doing a hardware upgrade in Belfast Hall.  All work should be completed by 7:00 am.


Networkmaine Contact Info: 
	NOC 561-3587

Local/Campus Contact Info during this window of work: 
	NONE / Unknown at this time