GW-O-Neville chassis has been replaced and the Network part of this
maintenance is complete and everything looks like it is up and running like
it should. The work on the Data Center is still ongoing.
Corey Lavoie
============================================
== Senior Communications Specialist
== Communications and Network Services
== Maine School and Library Network
== University of Maine System
============================================
On Tue, Mar 19, 2013 at 12:47 PM, Corey D Lavoie <[log in to unmask]> wrote:
> Where: Orono Campus / UMS-ITS Orono Data Center
> When: Mar 24, 2013 5:00 AM
> Expected Duration: 5hrs
> Scope: UMS Connections in/out of Orono
>
> Summary:
> This is an advanced notice of the previous cancelled maintenance.
> During the maintenance window we will be replacing the hardware for
> GW-O-Neville.
>
> This will create an outage for the Orono Campus (UM IP Phones as well) and
> access to the Orono Data Center from the rest of the University of Maine
> System. This will affect access to service such as MaineStreet,
> http://www.maine.edu, and all other services running out of the Orono
> Data Center.
>
> Systems group will also be working on some updates to the infrastructure
> of the Data Center so there will be some downtime with their systems as
> well.
>
> Total downtime should be around two hours for the network, but remaining
> time in the maintenance window may be needed to resolve any issues that may
> be related to the maintenance.
>
> Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
|
|
|