10 Gig board has been replaced.
Switches in Mahaney Clubhouse and Jennness Hall were swapped out.
Cat-O-Jenness2 was removed from service as it has not been used for 2
years.
Work in McKay Archaeological Lab was not complete as it was past 7:00 am.
We will look to complete this work next week.
Thank you,
Corey Lavoie
============================================
== Senior Communications Specialist
== Communications and Network Services
== Maine School and Library Network
== University of Maine System
============================================.
On Mon, Jan 28, 2013 at 3:30 PM, Corey D Lavoie <[log in to unmask]> wrote:
> Where: Orono Campus / UMS-ITS Orono Data Center
> When: Jan 28, 2013 5:00 AM
> Expected Duration: 2hrs
> Scope: Network connectivity in some buildings
>
> Summary:
> During the maintenance window we will be doing some maintenance on
> some failed hardware that may affect connectivity to the Data Center.
> There is another path to the Data Center so this should be non-service
> affecting.
>
> Also during the maintenance window we will be replacing equipment in the
> following buildings:
>
> Jenness Hall,
> Mahaney Clubhouse,
> McKay Archeological Lab
>
> All work should be completed by 7:00 am.
>
> Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
|
|
|