Where: ADVANCED NOTICE Orono Campus / UMS-ITS Orono Data Center
When: 5:00 AM
Expected Duration: 6 Hours
Scope: UMS and MSLN Connections in/out of Orono
Summary:
Work Scheduled for April 15, 2012.
During the maintenance window we will be doing some work in the UMS-ITS Orono Data Center that will affect network connectivity for the University of Maine Campus and to the Data Center. We are going to try and minimize down time, but all work should be completed by 11:00 AM. List of sites affected by work is a follows and may not be all inclusive:
All connections to UMS-ITS Orono Data Center (MaineStreet, Blackboard, email services, Any VM hosted machine, etc.),
All buildings on University of Maine Campus,
FBRI (Old Town Mill),
Target Tech,
Networkmaine Contact Info:
NOC 561-3587
Local/Campus Contact Info during this window of work: