Todd Boynton <[log in to unmask]>
Reply To:
- NETANN-L - Networkmaine Network Announcement List <[log in to unmask]>
Date:
Wed, 19 Oct 2011 06:14:23 -0400
Content-Type:
text/plain
Parts/Attachments:
text/plain (37 lines)
Portland datacenter has lost power.  ETA for power restoration is 6:30.

On Fri, Oct 14, 2011 at 5:30 AM, Dave Norton <[log in to unmask]> wrote:
> Where: Portland Datacenter
> When: 5:00am
> Expected Duration: 2hrs
> Scope: Power work on the datacenter feed
>
> Summary:
>        Work will start at 5:00am on the datacenter electrical feed to migrate the datacenter to a temporary power source so that work can be done on the transformer and feed.  After work is completed, we'll be cut back over to our regular electrical feed from temporary power.
>
> At this time, we don't expect downtime due to any power loss to the equipment.  UPS' will carry things during the cut-overs.
>
>
>
> Details:
>
>
> Networkmaine Contact Info during the window for this work:
>        [log in to unmask]
>        NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
>        NONE / Unknown at this time
>



-- 
Todd Boynton
University of Maine System
Unified Communications Analyst
Networkmaine

(207)561-3549
[log in to unmask]