All work for UMFK Cyr Hall has been complete. Equipment is now connected
to new UPS. New switches have been installed. Cat-k-cyr name has changed
to Cat-k-cyr2. We have added new Cat-k-cyr1 to Cyr hall.
Corey
On Aug 9, 2012 3:39 PM, "Corey D Lavoie" <[log in to unmask]> wrote:
> Where: UMFK Cyr Hall
> When: Aug 12, 2012 5:00 AM
> Expected Duration: 4hrs
> Scope: Network Connectivity on UMFK campus
>
> Summary:
> During the maintenance window, we will be doing some network
> equipment upgrades, this will affect connections for the following
> buildings:
>
> Acadian Archives
> Crocker Hall
> Cyr Hall
> Fox
> Nadeau Teleconference Room
> Nowland Hall
> Old Crocker Hall
> Physical Plant.
>
> All work should be complete by 9:00 AM.
> Powell Hall
>
>
> Networkmaine Contact Info:
> NOC 561-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>