On Wed, Aug 2, 2023 at 4:53 PM <[log in to unmask]> wrote:
> Where: UMF
> Start: 08/04/2023 05:00 am
> End: 08/04/2023 07:00 am
> Scope: UMF LAN
>
> Summary:
> Taking advantage of an existing planned site visit, the campus
> core switch and the following building switches will undergo a firmware
> update:
>
> cat-f-fitness-center-bdf.net.maine.edu
> cat-f-admissions-bdf.net.maine.edu
> cat-f-mantor-bdf.net.maine.edu
> cat-f-scott-bdf.net.maine.edu
> cat-f-scott-idfb.net.maine.edu
> cat-f-149quebec-bdf.net.maine.edu
> cat-f-merrill-bdf.net.maine.edu
> cat-f-olsen-bdf.net.maine.edu
> cat-f-preble-bdf.net.maine.edu
> cat-f-ferro-bdf.net.maine.edu
> cat-f-center-bdf.net.maine.edu
> cat-f-franklin-bdf.net.maine.edu
> cat-f-olsen-idf.net.maine.edu
> cat-f-scott-idfc.net.maine.edu
>
>
> Details:
>
>
> Networkmaine Contact Info during the window for this work:
> [log in to unmask]
> NOC 581-3587
>
> Local/Campus Contact Info during this window of work:
> NONE / Unknown at this time
>
--
Jason McDonald
Network Engineer II
Networkmaine, University of Maine System